Whole-home update before move-in
New floors, two bathrooms, paint and a kitchen refresh in the weeks between closing and move-in.
- Location
- Pembroke Pines
- Service
- Full home renovation
- Timeline
- 7 weeks
- Budget
- $$$$


The problem
A tight window between closing and the family's lease ending, with four trades to coordinate.
What we did
- 1Phased schedule shared with the owners on day one
- 2Flooring and paint run in parallel across zones
- 3Two bathrooms remodeled back to back
- 4Kitchen refreshed with painted cabinets, new counters and backsplash
The result
The family moved in on schedule to a home that felt new.